NEW YORK (BLOOMBERG) - The United States Army's initial estimate that it may spend nearly US$22 billion (S$30.2 billion) over the next decade on high-tech combat goggles and related services from Microsoft may be double what the service really expects.
Pushing back on criticism in a report Friday (April 22) from the Pentagon's inspector general that the contract "could result in wasting up to US$21.9 billion in taxpayers funds to field a system that soldiers may not want to use or use as intended", the Army said the estimate was a worst-case scenario and a ceiling for what the service would expect to spend.
"Less than half of this total is possible for the US Army," according to the rebuttal by Army Assistant Secretary for Acquisition Douglas Bush.
The US$21.9 billion figure that has been seen by some investors and analysts as possible revenue for Microsoft represents "a contract ceiling that includes all possible hardware, components, and services over a 10-year period at the worst possible pricing structure", it continued. The full estimate includes "all possible sales to sister services, foreign military sales and all maximised service contracts", according to Mr Bush's response.
Microsoft's Integrated Visual Augmentation System, or IVAS, is expected to provide a "heads-up display" for US ground forces, similar to those for fighter pilots. The system - a customised version of Microsoft's HoloLens goggles - would let commanders project information onto a visor in front of a soldier's face and would include other features such as night vision.
But the system has already faced delays and other hurdles. Despite progress since the initial development contracts Bloomberg News reported in January that the system "has not yet demonstrated the capability to serve as a fighting goggle", according to an assessment by the Pentagon's director of operational testing that was sent to the Army for review.
The Army announced in October a delay in fielding the programme to allow more time to prepare for the intense combat testing needed for full-rate production and initial fielding. T
he test, previously scheduled for last September, was tentatively re-scheduled for between May 23 and June 25 and will result in a "Rapid Fielding Report" from the Pentagon testing office. Mr Bush will evaluate the report to determine whether the goggles should be fielded and go into full production.
An official at Redmond, Washington-based Microsoft said via e-mail that the company continues to develop IVAS as a "transformational platform" that will enhance soldier safety and effectiveness, without addressing the potential contract size.
Redacted audit
On Friday, the inspector general's heavily-redacted audit concluded that the Army made mistakes in the programme's initial stages in not clearly delineating minimum performance standards the devices must meet during soldier acceptance tests. The audit stressed - as the service has - the importance of soldier feedback and acceptance during a series of five increasingly complex "Capability Set" exercises.
"However, programme officials did not define clear measures of user acceptance to determine whether IVAS would meet user needs."
Mr Bush, in his rebuttal, also disagreed with the overall thrust of the inspector general's report. He said the watchdog's conclusion about potential wasted taxpayer dollars was "fundamentally flawed and inflammatory and must be removed or rewritten" because "it is a biased word, intended to illicit an emotional response".
The report retained the phrase but censored as "Controlled Unclassified Information", or CUI, large chunks of the report, including the conclusions section. The redactions and CUI markings usually come at the recommendation of the individual services or the department.