S’pore’s World Aquatics Championships Arena to reopen in 2027
Sign up now: Get the biggest sports news in your inbox
The World Aquatics Championships Arena was originally slated to reopen in the second quarter of 2026.
ST PHOTO: LIM YAOHUI
- Sport Singapore said the WCH Arena in Kallang will now reopen in the second quarter of 2027 after extra reinforcement works are needed.
- Engineers found ground settlement from soft marine clay, so the foundation must be strengthened to keep the pools safe and stable.
- The arena, used for the 2025 World Aquatics Championships, will later serve the public, national athletes, and major events such as the SEA Games and Asean Para Games.
AI generated
SINGAPORE – The World Aquatics Championships (WCH) Arena in Kallang is targeted to reopen in the second quarter of 2027, national agency Sport Singapore (SportSG) announced on Oct 7.
In a media statement, a SportSG spokesperson gave an update on the timeline of the WCH Arena, which was originally slated to reopen in the second quarter of 2026. The spokesperson said the new reopening date is due to the need for additional reinforcement works to “address unforeseen ground conditions identified during construction”.
Built at a carpark next to the Leisure Park Kallang mall, the WCH Arena hosted the swimming and artistic swimming events of the World Aquatics Championships in 2025.
SportSG said the facility was opened for public use in end-2025 and in January 2026, it was closed for enhancement works to meet regulatory requirements and support its extended use as a public sport facility.
The spokesperson said: “In the first quarter of 2026, engineering assessments identified ground settlement issues due to the underlying soft marine clay.
“Following further technical studies, it was determined that additional reinforcement works were necessary to strengthen the foundation supporting the pools and ensure the long-term integrity of the pool structures.
“Carrying out the necessary reinforcement works now is essential to ensure that the facility is safe for our users. The reinforcement works are underway, and we are working closely with our contractors and relevant agencies to complete all the works safely and in accordance with the required standards.
“When it reopens in 2027, the WCH Arena is expected be an important venue for community use and major aquatics events.”
In October 2025, then Acting Minister for Culture, Community and Youth David Neo said that the WCH Arena would not be removed but would be open for national athletes and public use until 2030.
The decision to keep the arena was made following the completion of a feasibility study.
The WCH Arena will complement existing ActiveSG swimming facilities, and will be open for both public use and national team training.
It may be used to host future events such as the SEA Games and ASEAN Para Games when the Republic stages the biennial regional meets in 2029, with the nearby 3,000-seat OCBC Aquatic Centre also capable of hosting international events such as the World Para Swimming Championships.
The WCH Arena features Olympic-size competition and training pools and the same red OSB11 starting blocks used at the Paris Olympics in 2024.