150km of MRT power cables to be replaced

Trip coils along Tuas West Extension will also be replaced, following 3-line MRT breakdown

Commuters stranded at Queenstown MRT station after the three-line MRT breakdown on Oct 14 that affected 123,000 commuters.
Commuters stranded at Queenstown MRT station after the three-line MRT breakdown on Oct 14 that affected 123,000 commuters. ST PHOTO: DESMOND WEE

All electrical power cables along the Tuas West Extension will be replaced following a massive three-line MRT breakdown which left more than 6,700 passengers stuck on stranded trains for up to three hours on Oct 14.

In a joint briefing with rail operator SMRT and systems supplier Alstom yesterday, the Land Transport Authority (LTA) said the French company will replace some 150km of cables which supply power to trains by the end of next year.

The replacement cables will have tougher insulation, Alstom indicated. It will also replace all 113 trip coils - core components of circuit breakers - along the three-year-old western stretch of the East-West Line by the end of this year. The company will do so at its own cost, which it did not divulge.

SMRT said the Oct 14 breakdown during the evening peak hour affected around 123,000 commuters - 110,000 on the North-South and East-West Lines for 31/2 hours; as well as 13,000 on the Circle Line for just over an hour.

The massive disruption was traced to a burnt section of cables between Tuas Link and Tuas West Road stations.

The fault would have been isolated by circuit breakers in the vicinity, but one failed to trip as designed to because of a faulty trip coil.

This caused a secondary protection system to trip, cutting power supply from a Tuas substation to a stretch of stations along the North-South and East-West Lines.

SMRT then decided to draw power from an alternative substation in Buona Vista. But it did so without first isolating the power fault in Tuas, and hence allowed the electrical glitch to affect the Circle Line.

SMRT chief executive Neo Kian Hong said a staff member and a supervisor had misread equipment at the substation and thought the fault had been isolated. The two have since been suspended from duty, he added.

Remote video URL

It was revealed at the briefing that four similar cable faults had been detected since the Tuas West Extension opened in 2017.

These earlier faults did not lead to any widespread service disruption because circuit breakers meant to isolate them worked, LTA said.

It raised the matter of the faulty cables with Alstom in January this year and the contractor agreed to replace the upper layer of cables. Replacement work was to have started this month.

Mr Neo had also said trip coils along the affected stretch were last checked on Oct 6, just a week before the breakdown.

LTA said there will be early closures and late openings on weekends from next month to facilitate the trip coil replacement.

There may be full-day closures on Sundays next year when the cable replacement takes place.

LTA said the affected cables were of similar design and made by the same manufacturer as those in other parts of the MRT network.

Remote video URL

The circuit breakers are also of "established design" and widely used in the power industry.

On its part, SMRT said it will now test circuit breakers every six months instead of 12.

The operator added that it will "enhance procedures for power recovery" so that the human error which allowed the Oct 14 fault to spread to the Circle Line "will not recur".

This is not the first time power cables on a relatively new line are being replaced. In 2012, when the Circle Line was around three years old, 120km of its cables - also laid by Alstom - was replaced with more water-resistant cables at a cost of $15 million. The bulk of the replacement cost was borne by Alstom.

At yesterday's briefing, the French contractor said it was still investigating what caused the cables and trip coils to fail.

LTA's new chief executive Ng Lang, just over a month into the job, said the breakdown was a stark reminder that the work to keep the rail system reliable was an unending journey which could be disrupted by the smallest of faults.

• Additional reporting by Clement Yong

Join ST's WhatsApp Channel and get the latest news and must-reads.

A version of this article appeared in the print edition of The Straits Times on October 29, 2020, with the headline 150km of MRT power cables to be replaced. Subscribe