Court reverses conviction for sewerage contractor

It says firm not liable for offence by subcontractor which had damaged a water main, orders refund of $50k fine

Sign up now: Get ST's newsletters delivered to your inbox

A drill worker investigating a site for a new sewerage system struck a main pipe, causing more than 7,000 cubic m of water to gush out - enough to fill three Olympic-size swimming pools.
It took eight hours for PUB engineers to isolate the main, and the contractor was billed for repairs totalling more than $122,000.
See more on